EQS-News: Vulcan Energy Resources Limited
/ Key word(s): Miscellaneous
Commissioning commences at Vulcan’s Lithium Extraction Optimisation Plant Major milestone for Vulcan Significant step forward for the EU battery critical raw materials supply chain
Vulcan Energy Resources Limited (Vulcan; ASX: VUL, FSE: VUL, the Company), the renewable energy producer and carbon neutral lithium developer, has commenced commissioning at its Lithium Extraction Optimisation Plant (LEOP).
Highlights:
CEO, Cris Moreno, stated: "The commencement of the commissioning of our LEOP facility represents a significant milestone for us, as well as the entire European battery industry. By 2030, Europe is likely to face a significant lithium shortage, which could have serious implications for the European battery and automotive industries if domestic supplies are not realised. Vulcan is gearing up to be the first to produce lithium from Europe, for Europe, but also to be the first company worldwide to produce carbon neutral lithium. The start of the commissioning of our LEOP facility is a key step toward the implementation of Phase One of our Zero Carbon Lithium™ Project, and in enabling a secure and independent European supply chain for Lithium. This is a great achievement of a determined team. Our pilot plants have already demonstrated the capability of A-DLE, a technology that has been commercially in use globally for decades, on our brines. With this determination, we will continue to advance in the coming months, driving the mobility transition in Europe, and serving as an inspiring example of what is possible, pioneering a carbon free future. “
About LEOP Vulcan’s LEOP has been built to enable operational readiness when construction of the full commercial plant is completed, to reduce commercial ramp up time. LEOP has the same equipment that Vulcan’s commercial LEP will have, with adsorption columns at a 1:50 scale of the commercial unit, with a greater number of columns in the commercial plant. The LEOP will have the capacity to produce approximately 100 tonnes of lithium chloride solution per annum. The production volumes at LEOP will signify the first tonnes of lithium chloride concentrate domestically produced in Europe, and the first tonnes of lithium produced using the commercially proven method of Adsorption – type Direct Lithium Extraction (A-DLE) powered from renewable heat instead of gas. Figure 1. Vulcan's Lithium Extraction Optimisation Plant at Landau
Figure 2. Crystalliser installation
Figure 3. Brine Conditioning System
About Vulcan Founded in 2018, Vulcan’s unique Zero Carbon Lithium™ Project aims to decarbonise lithium production, through developing the world’s first net carbon neutral lithium business, with the co-production of renewable geothermal energy on a mass scale. By adapting existing technologies to efficiently extract lithium from geothermal brine, Vulcan aims to deliver a local source of sustainable lithium for Europe, built around a net zero carbon strategy with exclusion of fossil fuels. Already an operational renewable energy producer, Vulcan will also provide renewable electricity and heat to local communities. Vulcan’s combined geothermal energy and lithium resource is the largest in Europe18F[1], with license areas focused on the Upper Rhine Valley, Germany. Strategically placed in the heart of the European electric vehicle market to decarbonise the supply chain, Vulcan is rapidly advancing the Zero Carbon Lithium™ Project to target timely market entry, with the ability to expand to meet the unprecedented demand that is building in the European markets. Guided by our Values of Integrity, Leadership, Future-focused and Sustainability, and united by a passion for the environment and leveraging scientific solutions, Vulcan has a unique, world-leading scientific and commercial team in the fields of lithium chemicals and geothermal renewable energy. Vulcan is committed to partnering with organisations that share its decarbonisation ambitions and has binding lithium offtake agreements with some of the largest cathode, battery, and automakers in the world. As a motivated disruptor, Vulcan aims to leverage its multidisciplinary expert team, leading geothermal technology and position in the European EV supply chain to be a global leader in producing zero fossil fuel, net carbon neutral lithium while being nature positive. Vulcan aims to be the largest, most preferred, strategic supplier of lithium chemicals and renewable power and heating from Europe, for Europe; to empower a net zero carbon future. Corporate Directory
Executive Chair Dr. Francis Wedin Managing Director and CEO Cris Moreno Deputy Chair Gavin Rezos Non-Executive Director Ranya Alkadamani Non-Executive Director Annie Liu Non-Executive Director Dr. Heidi Grön Non-Executive Director Josephine Bush Non-Executive Director Dr. Günter Hilken Non-Executive Director Mark Skelton Executive Director, Germany Dr. Horst Kreuter
Company Secretary Daniel Tydde
For and on behalf of the Board Daniel Tydde | Company Secretary
Media and Investor Relations contact Annabel Roedhammer, Director, Communications and Investor Relations and PR | aroedhammer@v-er.eu | +49 1511 410 1585 Please contact Vulcan’s Legal Counsel Germany, Dr Meinhard Grodde, for matters relating to the Frankfurt Stock Exchange listing on mgrodde@v-er.eu.
Reporting calendar
Disclaimer Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which Vulcan operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement. No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside Vulcan’s control. Vulcan does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of Vulcan, its Directors, employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement. This announcement is not an offer, invitation or recommendation to subscribe for, or purchase securities by Vulcan. Nor does this announcement constitute investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used for the basis of making an investment decision. Investors should obtain their own advice before making any investment decision. Vulcan has carried out a definitive feasibility study for Phase One of its Zero Carbon Lithium™ Project ('Project'), the results of which were announced to the ASX in the announcement "Zero Carbon Lithium Project Phase 1 DFS Results" dated 13 February 2023 ('DFS'), ('DFS Announcement'). This announcement may include certain information relating to the DFS. The DFS is based on the material assumptions outlined in the DFS Announcement (see "Competent Person Statement" below). While Vulcan considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct of that the range of outcomes indicated by the DFS will be achieved. This announcement may also include certain information relating to Phase 2 of its Project, Vulcan has not yet carried out a definitive feasibility study for Phase Two of its Project.
Competent Person Statement: The information in this announcement that relates to Mineral Resources and Ore Reserves, and any Exploration Results and Production Targets, of Vulcan's Zero Carbon Lithium Project is extracted from the DFS Announcement, which is available to view on Vulcan's website at www.v-er.eu. Vulcan confirms that in respect of estimates of Mineral Resources and Ore Reserves, and any Exploration Results and Production Targets, included in this announcement:
[1] According to public, JORC-compliant data. See Phase One DFS announcement, 13 February 2023.
17.08.2023 CET/CEST Dissemination of a Corporate News, transmitted by EQS News - a service of EQS Group AG. |
Language: | English |
Company: | Vulcan Energy Resources Limited |
Level 2,267 St. Georges Terrace | |
6000 Perth | |
Australia | |
E-mail: | dtydde@v-er.eu |
Internet: | www.v-er.eu |
ISIN: | AU0000066086 |
WKN: | A2PV3A |
Listed: | Regulated Market in Frankfurt (Prime Standard); Regulated Unofficial Market in Berlin, Dusseldorf, Hamburg, Munich, Stuttgart, Tradegate Exchange |
EQS News ID: | 1705867 |
End of News | EQS News Service |
|
1705867 17.08.2023 CET/CEST
The information presented here has been provided by our content partner EQS-Group. The originator of the news is the respective issuer, the company relating to the news, a publication service provider (press or information agency) which uses the distribution service of EQS to transmit company news to shareholders, investors, investors or interested parties. The original publications and other company-relevant information can be found at eqs-news.com.
The information you can access does not constitute investment advice. The presentation of our cooperation partners, where the implementation of investment decisions would be possible depending on the individual risk profile, is solely at the discretion of the person using the service. We only present companies of which we are convinced that the range of services and customer service will satisfy discerning investors.
If you are considering leverage products, familiarise yourself with the typical characteristics of the financial instruments beforehand. Take the time to determine the risk content of the planned investment before making an investment decision. Bear in mind that a total loss cannot be ruled out with leverage products.
For newcomers to the subject, we offer various options in both the training and the tools section, through which you can train theoretical knowledge and practical experience and thus improve your skills. The offer ranges from participation in webinars to personal mentoring. The range is continuously being expanded.
1 Lab features are usually functionalities that emerge from the think tank of the investor community. In the early stages, these are experimental functionalities whose development process is largely determined by use and the resulting feedback from the community. When integrating external services or functionalities, the functionality can only be guaranteed to the extent that the individual process elements, such as interfaces, interact with each other.